April 29, 2016 – Broadway Water Main Project

Phases 1 & 2 (Bryn Mawr to Thorndale);

  • Service connections have been made up to Rosedale Avenue.
  • Connections from Rosedale to Thorndale are scheduled for week of May 2
  • Concrete cap work is set to begin Monday May 2 on Broadway going northward

Phases 3 & 4 (Bryn Mawr to Foster):

  • Water main installation continues, and pressure testing could start the week of May 2
  • A water shutdown may occur from Balmoral to Bryn Mawr on May 4 or May 5.
  • Hydrant replacement continues