August 19, 2016 – Ridge Water Main Project

All lanes of Ridge Ave. are open to traffic! See details below:

Phase 1 & 2 (Clark Street to Broadway):

  • The work on these sections is complete, and all lanes are once again open to traffic.

Phase 3 (Portions of Wayne and Hollywood Avenues):

  • Chlorination of the new pipe is taking place today (August 19).
  • Service transfers should begin Tuesday August 23, with brief water shutoffs scheduled. All affected residents will receive a flyer in advance of the shutoffs.
  • The concrete cap will likely be installed the week of August 29.

Phase 4 (Wayne from Ridge to Early):

  • Pipe installation is taking place today and may continue into Monday August 22. Service transfers and brief water shutoffs could take place as early as Friday August 26.
  • The concrete cap will likely be installed the week of August 29.

Click here for the water flushing instructions given to all residences and businesses in the vicinity of the new water main.